The National Gas Company of Trinidad and Tobago Limited (NGC) will construct a natural gas pipeline and metering station from the Couva-Preysal Interchange, Preysal Roundabout, to NGC CNG’s proposed Preysal CNG Station, at the same site.

Major works include the construction of a 4-inch diameter pipeline approximately five metres long and a metering station. There will be no disruption to the road surface nor to traffic flow.

Duration of Works: 100 calendar days

  • Commencement Date: 2nd September, 2019

  • Days of Work: Monday to Friday

  • Hours of Work: 7:00am to 5:00pm

Comment