The topsides lifting campaign for the Liza Unity FPSO was recently completed and a major project milestone was achieved. According to SBM, over 26,000 tons of topsides were safely lifted in position at Keppel Shipyard in Singapore, since the vessel came out of dry-dock in October of last year.
SBM indicated that all efforts are now focused on further progressing and completing the integration activities and gradually ramping-up the onboard commissioning activities.
The FPSO Liza Unity represents SBM Offshore’s first Fast4Ward® design, benefitting from standardization of the project`s execution plan and using a fully completed and commissioned MPF hull, which sets the benchmark for future FPSO projects. The project continues to target first oil in 2022 in line with client planning.